2013-04-29
15:53
SAFETY / C. Schaefer and N. Dupont
  “Safety is the highest priority”: this statement from CERN is endorsed by the CMS management. An interpretation of this statement may bring you to the conclusion that you should stop working in order to avoid risks. [...]
CMSBUL-ARTICLE-2013-018.- 2013 - Published in : , no. 1/2013, pp. 18

დეტალური ჩანაწერი - მსგავსი ჩანაწერები
2013-04-29
15:52
UPGRADES / D. Contardo and J. Spalding
  LS1 and Phase 1 The detector projects targeting LS1 are progressing well, and a fully integrated schedule developed by Technical Coordination includes installation milestones and a detailed work-plan. The first chambers of the RPC system were produced and are being qualified. [...]
CMSBUL-ARTICLE-2013-017.- 2013 - Published in : , no. 1/2013, pp. 17

დეტალური ჩანაწერი - მსგავსი ჩანაწერები
2013-04-29
15:50
PHYSICS / C. Hill
The period since the last CMS bulletin has seen the end of proton collisions at a centre-of-mass energy 8 TeV, a successful proton-lead collision run at 5 TeV/nucleon, as well as a “reference” proton run at 2.76 TeV. With these final LHC Run 1 datasets in hand, CMS Physics Analysis Groups have been busy analysing these data in preparation for the winter conferences. [...]
CMSBUL-ARTICLE-2013-016.- 2013 - Published in : , no. 1/2013, pp. 16

დეტალური ჩანაწერი - მსგავსი ჩანაწერები
2013-04-29
15:42
PHYSICS PERFORMANCE AND DATASET (PPD) / L. Silvestris ; P. Azzi ; C. Cerminara ; with contributions from R. Castello ; M. De Mattia ; A. Pfeiffer ; F. De Guio ; S. Dutta ; M. Rovere ; G. Boudoul et al.
  The PPD activities, in the first part of 2013, have been focused mostly on the final physics validation and preparation for the data reprocessing of the full 8 TeV datasets with the latest calibrations. These samples will be the basis for the preliminary results for summer 2013 but most importantly for the final publications on the 8 TeV Run 1 data. [...]
CMSBUL-ARTICLE-2013-015.- 2013 - Published in : , no. 1/2013, pp. 15

დეტალური ჩანაწერი - მსგავსი ჩანაწერები
2013-04-29
15:34
OFFLINE / L. Sexton-Kennedy ; F. Cossutti ; P. Elmer with contributions from A. Giammanco ; M. Hildreth ; V. Ivantchenko ; V. Krutelyov ; T. Speer ; V. Adler ; G. Kukartsev ; C. Jones and G. Eulisse.
The CMSSW_5_3_X cycle has successfully accomplished its main mission to support data taking up to the end of the LHC run, coping with the highest luminosities provided by the machine. It is foreseen to be kept active for the whole of 2013 at least as the legacy analysis release for 2012 data. [...]
CMSBUL-ARTICLE-2013-014.- 2013 - Published in : , no. 1/2013, pp. 14

დეტალური ჩანაწერი - მსგავსი ჩანაწერები
2013-04-29
15:30
RUN COORDINATION / G. Rakness.
After three years of running, in February 2013 the era of sub-10-TeV LHC collisions drew to an end. Recall, the 2012 run had been extended by about three months to achieve the full complement of high-energy and heavy-ion physics goals prior to the start of Long Shutdown 1 (LS1), which is now underway [...]
CMSBUL-ARTICLE-2013-013.- 2013 - Published in : , no. 1/2013, pp. 13

დეტალური ჩანაწერი - მსგავსი ჩანაწერები
2013-04-29
15:28
DAQ / J. Hegeman
The DAQ2 system for post-LS1 is a re-implementation of the central DAQ event data flow with the capability to read-out the majority of legacy back-end sub-detector electronics FEDs, as well as the new MicroTCA-based back-end electronics (see for example the previous (December 2012) issue of the CMS bulletin). A further upgrade in the DAQ and Trigger is the development of the new TCDS, outlined in the forthcoming Level-1 Trigger Upgrade TDR. [...]
CMSBUL-ARTICLE-2013-012.- 2013 - Published in : , no. 1/2013, pp. 12

დეტალური ჩანაწერი - მსგავსი ჩანაწერები
2013-04-29
15:23
TRIGGER / R. Arcidiacono ; A. Avetisyan ; A. Bocci ; G Christopher ; A. Perrotta and M. Vander Donckt.
  In 2013 the Trigger Studies Group (TSG) has been restructured in three sub-groups: STEAM, for the development of new HLT menus and monitoring their performance; STORM, for the development of HLT tools, code and actual configurations; and FOG, responsible for the online operations of the High Level Trigger. The Strategy for Trigger Evolution And Monitoring (STEAM) group is responsible for Trigger Menu development, path timing, trigger performance studies coordination, HLT offline DQM as well as HLT release, menu and conditions validation – in collaboration and with the technical support of the PdmV group. [...]
CMSBUL-ARTICLE-2013-011.- 2013 - Published in : , no. 1/2013, pp. 11

დეტალური ჩანაწერი - მსგავსი ჩანაწერები
2013-04-29
15:18
MUON DETECTORS: ALIGNMENT / Z. Szillasi and G. Gomez.
When CMS is opened up, major components of the Link and Barrel Alignment systems will be removed. This operation, besides allowing for maintenance of the detector underneath, is needed for making interventions that will reinforce the alignment measurements and make the operation of the alignment system more reliable. [...]
CMSBUL-ARTICLE-2013-010.- 2013 - Published in : , no. 1/2013, pp. 10

დეტალური ჩანაწერი - მსგავსი ჩანაწერები
2013-04-29
15:15
MUON DETECTORS: RPC / P. Paolucci
  In 2013 the main activities of the RPC project are: maintenance and repair of the present system, RE4 chambers installation, and commissioning and upgrade of the online and offline software. About 25 FTE are working on the three items since January and will continue until the end of 2014. [...]
CMSBUL-ARTICLE-2013-009.- 2013 - Published in : , no. 1/2013, pp. 9

დეტალური ჩანაწერი - მსგავსი ჩანაწერები