TRANSPORT/HANDLING REQUESTS

A new EDH document entitled 'Transport/Handling Request' will be in operation as of Monday, 11th February 2002, when the corresponding icon will be accessible from the EDH desktop, together with the application instructions.
This EDH form will replace the paper-format transport/handling request form for all activities involving the transport of equipment and materials. However, the paper form will still be used for all vehicle-hire requests.
The introduction of the EDH transport/handling request form is accompanied by the establishment of the following time limits for the various services concerned:
  • 24 hours for the removal of office items,
  • 48 hours for the transport of heavy items (of up to 6 metric tons and of standard road width),
  • 5 working days for a crane operation, extra-heavy transport operation or complete removal,
  • 5 working days for all transport operations relating to LHC installation.
ST/HM Group, Logistics Section
Tel: 72672 - 72202
by Groupe ST/HM