Single lane traffic in Adams road (Prévessin Site)
From 20th August, ST Division will be opening trenches in order to allow a number of power, control and optical fibre cables to be laid across Adams road (see plan).
For the duration of the work, the road will be barred to all heavy loads/lorries and alternative arrangements will be put in place for normal traffic. Temporary lights will be installed. We kindly ask all users to respect these temporary arrangements.
The work will take two weeks given favorable conditions.
Thank you for your understanding in this matter.
ST-EL Group
Tel. 72978 - 164082