Roof renovation of buildings 128 and 129

The roof renovation of buildings 128 and 129 is scheduled to take place from 17 August to 15 October 2015.

 

During this period, access to the "raw material" workshop will be limited and controlled due to asbestos removal. Collecting your orders directly from the building will be difficult, or even impossible, and urgent requests will be difficult to carry out.

We therefore ask you to create your requests via EDH, so that delivery may be carried out as soon as possible.

Thank you for your understanding.

GS Department