Since the last report, the commissioning with beam was delayed after a short to ground appeared in the cold mass of the main dipole chain in sector 3-4. After a remarkable team effort coordinated by the Machine Protection group, a procedure to burn away the small piece of metallic debris that was causing the earth fault was conceived, prototyped, tested and deployed. The intervention was successfully completed on the afternoon of 31 March and the first beams circulated in the LHC on Sunday, 5 April. Just a few days later, at just past midnight on Friday, 10 April, beam was ramped up to 6.5 TeV.
>>